  1. A large general contractor wants you on a big new-construction project with thin margins. Your service agreements carry most of your profit. How do you decide whether to bid?

    Situational · Choosing which work to chase

    Strong answer
    Weighs margin, cash flow and retainage, bonding capacity, crew availability, the contractor's payment history and the risk to service customers, then decides with clear limits.
    Red flags
    Bids every big job for the revenue.
  2. A competitor with a strong base of service agreements is for sale. How do you evaluate buying it?

    Situational · Acquisition judgment

    Strong answer
    Checks contract quality and renewal history, technician retention, margins, customer concentration, debt and integration costs, and plans how to keep the people.
    Red flags
    Looks only at revenue and price.
  3. A technician falls from a rooftop unit at a customer site and is seriously hurt. What do you do over the next week?

    Situational · Leading after a serious injury

    Strong answer
    Makes sure the worker and family get support, meets OSHA reporting rules, finds the root causes, fixes roof safety practices company-wide, and talks openly with the team.
    Red flags
    Focuses on liability first, or treats it as a one-off.
  4. Walk me through how you read a work-in-progress schedule to judge whether your projects are really making money.

    Technical · Reading job profit

    Strong answer
    Compares original and current estimated profit by job, looks for profit fade, over and under billing and rising cost to complete, and questions project managers on slipping jobs.
    Red flags
    Looks only at revenue or the bank balance.
  5. Tell me about a time your company's mistake on a construction project put a relationship with a key general contractor at risk.

    Behavioral · Key contractor relationships

    Strong answer
    Owned the mistake with the contractor's leadership, fixed it on the job, changed the process that caused it, such as submittals or crew planning, and can say honestly whether the relationship recovered.
    Red flags
    Blames the contractor or the project manager, or talks only about wins.
  6. Tell me how you tested candidates the last time you hired a service manager or senior project manager.

    Behavioral · Senior hiring

    Strong answer
    Explains what the role needed, how they tested it (a work-in-progress review, a scheduling exercise, references), how they set the new leader up to succeed, and the results.
    Red flags
    Hired someone they knew, or relied on a résumé and a friendly conversation.

Work exercise: Rank three opportunities

Give finalists a made-up summary of [three] opportunities: a large general contractor bid, a hospital service agreement and a small competitor for sale. Ask them to rank them and explain the risks, cash needs and staffing impact of each in [25] minutes.

Chief Operating Officer

6 questions · Plan a branch turnaround
Job description
  1. Your biggest property management customer says you missed their contract response times several times this month. What do you do?

    Situational · Meeting contract response times

    Strong answer
    Pulls the data, finds the causes (dispatch, staffing, after-hours coverage), fixes them, meets the customer with a plan, and reports progress.
    Red flags
    Apologizes without changing anything.
  2. You learn that one branch hasn't been keeping leak repair records on its large refrigerant systems. What do you do?

    Situational · Refrigerant compliance

    Strong answer
    Treats it as a compliance risk, finds which systems are affected, sets up records that meet current EPA rules, trains technicians, and audits it going forward.
    Red flags
    Tells the branch to do better.
  3. Construction projects keep pulling technicians off service, and service agreement customers are suffering. What do you do?

    Situational · Service vs. construction staffing

    Strong answer
    Sets clear staffing priorities, plans crew needs with project managers weeks ahead, hires or subcontracts to fill gaps, and tracks both sides.
    Red flags
    Lets whoever shouts loudest win.
  4. Walk me through how you'd set up a preventive maintenance program for a few hundred rooftop units across many customers.

    Technical · Building a maintenance program

    Strong answer
    Builds equipment lists, sets visit schedules and checklists by equipment type, plans routes, tracks completion and findings in the software, and turns findings into quotes.
    Red flags
    Leaves scheduling to each technician.
  5. Tell me about a time you took over a commercial service department that was missing response times or losing agreements.

    Behavioral · Turning around a team

    Strong answer
    Diagnosed the problems with data and ride-alongs, changed specific people or processes, set measures like response time and callbacks, and shows the results.
    Red flags
    Is vague, or claims improvement with nothing to measure it.
  6. Tell me about a time you had to decide quickly whether to pull technicians off a project to cover service emergencies.

    Behavioral · Service vs. project tradeoffs

    Strong answer
    Explains what they knew, the risk on each side, the decision, how they told customers and project managers, and what they changed so it happened less.
    Red flags
    Waited for the problem to sort itself out, or can't explain the reasoning.

Work exercise: Plan a branch turnaround

Give finalists a made-up month of data for [two] branches: response times, maintenance visits completed, callbacks and labor hours on projects. Ask them to name the biggest problem and present a [90]-day plan in [25] minutes.

Chief Financial Officer

6 questions · Review a WIP schedule
Job description
  1. Walk me through how you build and review the monthly work-in-progress schedule.

    Technical · Work-in-progress reporting

    Strong answer
    Updates cost to complete with project managers, calculates percent complete, recognizes revenue on that basis, books over and under billings, and investigates profit fade on each job.
    Red flags
    Treats billings as revenue, or never updates the estimates.
  2. A general contractor is two months late on a large pay application and payroll is growing. What do you do?

    Situational · Cash and slow payers

    Strong answer
    Finds out why, escalates through the project manager and the contractor's accounting team, reviews lien rights and deadlines, and updates the cash forecast and credit line plan.
    Red flags
    Waits, or stops work without checking the contract.
  3. Project managers are carrying a pile of unsigned change orders on active jobs. What do you do about it?

    Situational · Unsigned change orders

    Strong answer
    Totals the exposure, sets a weekly review, pushes for written approval before extra work where possible, and reflects the risk in the work-in-progress report.
    Red flags
    Counts them as revenue without approvals.
  4. Your data shows some preventive maintenance agreements lose money. What do you do?

    Situational · Service agreement profitability

    Strong answer
    Works out the true cost per visit including drive time, filters and belts, separates underpriced contracts from poorly run ones, and works with sales to reprice at renewal.
    Red flags
    Cancels them all, or ignores the losses.
  5. Tell me about a time you needed more bonding capacity or credit from a surety or bank to take on bigger HVAC projects.

    Behavioral · Bank and surety relationships

    Strong answer
    Describes timely, clean reporting, sharing bad news early with a plan, and the result for credit or bonding capacity.
    Red flags
    Hid bad news from the bank or surety until a covenant test or bond request forced it, or only signed renewals someone else prepared.
  6. Tell me about a time you pushed back when operations wanted to bid a large job or buy trucks or equipment the numbers didn't support.

    Behavioral · Pushing back on spending

    Strong answer
    Laid out the cash, margin or bonding numbers, offered an alternative such as leasing or a smaller bid, and either held the line or changed course for clear reasons.
    Red flags
    Always says yes, or says no without numbers.

Work exercise: Review a WIP schedule

Give finalists a made-up work-in-progress schedule for [five] commercial HVAC jobs, with one showing profit fade and one heavily overbilled. Ask them to explain what each tells them and list the questions they'd ask each project manager, in [30] minutes.

General Manager

6 questions · Set branch priorities
Job description
  1. Walk me through how you'd raise revenue per service hour without hurting customers.

    Technical · Revenue per service hour

    Strong answer
    Looks at billable versus paid hours, rates, unbilled extras, truck stock, drive time and quoting repairs found on maintenance visits, and watches customer satisfaction alongside.
    Red flags
    Just raises rates or pushes technicians to upsell.
  2. A project manager's install job is running over budget halfway through. What do you do?

    Situational · Rescuing a job over budget

    Strong answer
    Reviews cost to complete with the project manager, finds the causes (labor productivity, missed scope, unbilled changes), acts on change orders and the crew plan, and updates the forecast.
    Red flags
    Waits until the job ends to see the loss.
  3. A hospital customer threatens to cancel its service agreement after your team missed an after-hours emergency. What do you do?

    Situational · Saving a key account

    Strong answer
    Meets the customer quickly, owns the failure, explains the fix to on-call coverage, offers a fair remedy, and follows through.
    Red flags
    Blames the on-call technician.
  4. A large property management customer wants a rate cut at renewal or they'll put the work out to bid. What do you do?

    Situational · Renewal pricing pressure

    Strong answer
    Knows the account's true profit, offers scope or visit changes rather than blind cuts, and is willing to walk away if the price would lose money.
    Red flags
    Cuts the price to keep the account.
  5. Tell me how you prepared a strong commercial technician to lead other technicians.

    Behavioral · Developing managers

    Strong answer
    Names what they needed to learn (planning, coaching others, facility manager conversations, letting go of the tools), how they coached them, and how the person did in the new role.
    Red flags
    Promoted the best technician and left them to figure it out.
  6. Tell me about a time you let go of a high-producing technician over conduct at a customer's site.

    Behavioral · Acting on conduct

    Strong answer
    Documented the issues, followed policy, handled the customer impact, and explained the decision to the team appropriately.
    Red flags
    Avoided it because of the technician's production.

Work exercise: Set branch priorities

Give finalists a made-up monthly report for a commercial HVAC branch: revenue per service hour, callbacks, install schedule status and [two] customer complaints. Allow [10] minutes to prepare, then have them run a [15]-minute mock meeting with two of your managers.

Field Supervisor

6 questions · Review a rooftop job
Job description
  1. Walk me through what you check before you sign off on a rooftop unit replacement.

    Technical · Rooftop unit sign-off

    Strong answer
    Curb and adapter sealed, unit secured, gas and electrical connections, condensate trap, economizer and controls operation, airflow and startup readings, safety switches, and the roof left clean and undamaged.
    Red flags
    Checks that it runs and blows cold.
  2. You find a technician working inside a rooftop unit with the disconnect off but no lock or tag, and the building engineer nearby. What do you do?

    Situational · Lockout/tagout

    Strong answer
    Stops the work, has the technician lock and tag out with their own lock and verify zero energy, and talks with the crew about why it matters.
    Red flags
    Lets them finish because the disconnect is off.
  3. Your crew needs to shut off heat in an occupied office building for a day during a cold snap to swap a boiler. How do you plan it?

    Situational · Shutdowns in occupied buildings

    Strong answer
    Agrees on timing with the building manager, arranges temporary heat and tenant notices, stages crew and materials before shutdown, and has a backup plan if it runs long.
    Red flags
    Starts the work and hopes it finishes on time.
  4. One technician's callback rate is far higher than the rest of the team. What do you do?

    Situational · Coaching on callbacks

    Strong answer
    Reviews the callbacks, rides along, finds the skill or habit gap, coaches on specifics, and checks the numbers again.
    Red flags
    Writes them up without finding the cause.
  5. Tell me about a time you stopped work for safety on a rooftop or mechanical room job.

    Behavioral · Stopping unsafe work

    Strong answer
    Names the hazard (roof edge, energized equipment, confined space), stopped the work, fixed it, and explained why to the crew.
    Red flags
    Has never had to, or let it go.
  6. Tell me about a time a facility manager was unhappy with your team's work, like comfort complaints after a changeout or a mess left on the roof.

    Behavioral · Facility manager relations

    Strong answer
    Met them, listened, checked the facts on site, fixed what was wrong, and followed up.
    Red flags
    Defended the team without checking.

Work exercise: Review a rooftop job

Give finalists a made-up technician daily report with gaps and [four] photos of a made-up rooftop install with planted problems, such as an unsealed curb and a missing condensate trap. Ask them to list the issues and write the next day's plan in [20] minutes.

HR Manager

6 questions · Advise on a case file
Job description
  1. You need two technicians with chiller and building controls experience, and few exist in your market. What do you do?

    Situational · Recruiting specialized technicians

    Strong answer
    Works manufacturer, union, trade school and supply house networks, offers referral incentives, posts real pay and schedule, and considers training a strong internal technician.
    Red flags
    Posts an ad and waits.
  2. Walk me through how you'd track technicians' certifications, licenses, safety training and the site badges some customers require.

    Technical · Tracking credentials

    Strong answer
    Keeps a central tracker with expiration dates and copies on file, sends reminders well ahead, shares status with dispatch, and has a rule that expired credentials mean no assignments that require them.
    Red flags
    Relies on employees to say when something expires.
  3. New technicians keep quitting within their first three months. What do you do?

    Situational · Early turnover

    Strong answer
    Talks with the people who left and their supervisors, checks the first weeks (truck, tools, mentoring, on-call), fixes the gaps, and tracks retention afterward.
    Red flags
    Blames the new hires.
  4. A technician asks for several weeks off for a medical procedure during the busiest month. What do you do?

    Situational · Leave during busy season

    Strong answer
    Follows company policy and leave laws such as FMLA and state leave where they apply, doesn't ask about the diagnosis, keeps medical details confidential, and works with the manager on coverage.
    Red flags
    Tells the technician to wait until the season ends.
  5. Tell me about a workplace investigation you led where the accused employee was one of the company's best technicians.

    Behavioral · Running investigations

    Strong answer
    Planned it, interviewed fairly, documented, reached a finding on the facts rather than the person's value, recommended action, and guarded against retaliation.
    Red flags
    Went easy because of the person's production, skipped steps, or decided before hearing both sides.
  6. Tell me about a time you rolled out a policy field employees opposed, such as vehicle use or on-call rules.

    Behavioral · Unpopular policy changes

    Strong answer
    Explained the reason, listened to field concerns, adjusted what was reasonable, trained supervisors to apply it consistently, and followed up.
    Red flags
    Imposed it with no explanation.

Work exercise: Advise on a case file

Give finalists a made-up case file: a supervisor's notes on a technician's [three] late arrivals, a lockout violation and a complaint the technician filed about the supervisor. Ask them to recommend next steps in writing in [25] minutes.

Marketing Manager

6 questions · Plan a target-account push
Job description
  1. Walk me through how you'd measure which marketing efforts lead to signed service agreements.

    Technical · Measuring business-to-business results

    Strong answer
    Tracks the source from first contact through the CRM to a signed agreement and its revenue, allows for long sales cycles, and reports cost per agreement.
    Red flags
    Reports website traffic or followers only.
  2. The owner wants more service agreements with schools and hospitals. How do you plan the marketing?

    Situational · Reaching institutional buyers

    Strong answer
    Learns who decides and how they buy (bids, requests for proposal, approved vendor lists), builds case studies and credentials, picks the right associations and events, and supports sales.
    Red flags
    Runs social media ads.
  3. Sales wants a case study about a job where the customer hasn't agreed to be named. What do you do?

    Situational · Customer permission

    Strong answer
    Gets written permission or removes identifying details, and checks every fact with the project team.
    Red flags
    Publishes it anyway.
  4. Your budget is cut by a third midyear. How do you decide what stays?

    Situational · Spending under a cut

    Strong answer
    Keeps what's proven to produce agreements, cuts what can't be measured, protects basics like the website and reviews, and explains the tradeoffs to the owner.
    Red flags
    Cuts evenly across everything.
  5. Tell me about a campaign aimed at facility managers or building owners that turned into signed work.

    Behavioral · Campaigns that closed business

    Strong answer
    Describes the audience, the offer and channels, how they tracked it to signed work, and the result.
    Red flags
    Can only point to clicks or awareness.
  6. Tell me about a time sales said your service agreement leads were the wrong buildings or the wrong contacts.

    Behavioral · Working with sales on lead quality

    Strong answer
    Looked at the data with sales, agreed on what a good agreement lead is (building type, equipment count, the person who decides), and changed targeting or the handoff.
    Red flags
    Blamed sales for not following up.

Work exercise: Plan a target-account push

Give finalists made-up profiles of [two] target customers: a regional hospital and a property management firm. Ask them to outline a [90]-day plan to win meetings with each and how they'd measure it, in [25] minutes.

Office Manager

6 questions · Clear work orders for billing
Job description
  1. Walk me through what you check before an invoice goes to a property management company.

    Technical · Billing documentation

    Strong answer
    Purchase order or work order number, not-to-exceed limit, signed ticket, rates from the agreement, tax status, required photos and the customer's portal rules.
    Red flags
    Sends whatever the system produces.
  2. Completed work orders are piling up because technicians haven't attached the signed tickets and photos customers require. What do you do?

    Situational · Closing out paperwork

    Strong answer
    Lists what's missing, works with the service manager to collect it, and changes closeout so jobs can't be closed without the required items.
    Red flags
    Chases each ticket one at a time and changes nothing.
  3. A new customer needs a certificate of insurance naming them as additional insured by tomorrow. What do you do?

    Situational · Certificates of insurance

    Strong answer
    Sends the insurance agent the exact wording the customer requires right away, checks the certificate before sending it, and tracks its expiration date.
    Red flags
    Sends an old certificate, or waits on the agent without following up.
  4. A customer's accounts payable team says it has no record of three invoices from last quarter. What do you do?

    Situational · Lost invoices

    Strong answer
    Pulls the invoices and proof of submission, resubmits through their process, confirms receipt, and tracks them until paid.
    Red flags
    Assumes they'll find them.
  5. Tell me about a time you cut the days between a finished work order and an invoice the customer's portal accepted.

    Behavioral · Shortening billing time

    Strong answer
    Names the bottleneck (missing signatures, portal rules, slow ticket review), the change made, and the before-and-after days from finished work to invoice.
    Red flags
    Blames technicians or customer portals, or names a change but can't say how many days it took off billing.
  6. Tell me about a time field and office staff blamed each other over an invoice a customer rejected.

    Behavioral · Bridging field and office

    Strong answer
    Got both sides together, looked at what the customer actually required, agreed on a fix both could live with, and checked that rejections dropped.
    Red flags
    Took a side without hearing both.

Work exercise: Clear work orders for billing

Give finalists [five] made-up completed work orders and [two] customers' billing rules, with planted problems like a missing purchase order and work over the not-to-exceed amount. Ask them to sort what can be billed today and what's needed for the rest, in [20] minutes.

Operations Manager

6 questions · Rebuild a two-week schedule
Job description
  1. Two jobs need a crane pick on the same Saturday, and only one crew is qualified to rig. What do you do?

    Situational · Allocating qualified crews

    Strong answer
    Checks which job can move, building owners' shutdown windows and crane availability, decides, tells project managers and customers early, and never sends an unqualified crew to rig.
    Red flags
    Sends the less experienced crew to the second pick.
  2. A rooftop unit is delayed four weeks, but the general contractor's schedule hasn't moved. What do you do?

    Situational · Long-lead equipment delays

    Strong answer
    Gets the new date in writing, tells the project manager and contractor early, looks at options like temporary cooling, adjusts crew plans and documents the delay.
    Red flags
    Waits and hopes it ships sooner.
  3. Technicians keep losing or damaging expensive tools like recovery machines and vacuum pumps. What do you do?

    Situational · Tools and test equipment

    Strong answer
    Sets up check-out tracking and truck audits, finds out whether the tools fit the work, sets clear responsibility, and replaces what's truly worn.
    Red flags
    Charges technicians for every loss without looking at the cause.
  4. Walk me through how you build a weekly schedule for service technicians and install crews.

    Technical · Building the weekly schedule

    Strong answer
    Starts with contract commitments and fixed dates, matches skills to work, plans routes, leaves room for emergencies, and confirms material and access before locking it.
    Red flags
    Fills the calendar first come, first served.
  5. Tell me about a change you made that cut return trips, like technicians arriving without the right parts or site access.

    Behavioral · Cutting wasted trips

    Strong answer
    Names the cause (no parts check, missing access details), the change (pre-call checklist, staging, access notes), and how much return trips dropped.
    Red flags
    Blames technicians or customers and changed nothing.
  6. Tell me about a time you had to tell a general contractor or building owner that a rooftop unit or crane date was going to slip.

    Behavioral · Delivering bad news on dates

    Strong answer
    Told them early, explained why without excuses, offered options like a partial start or temporary equipment, and kept the new date.
    Red flags
    Waited until the last minute, or blamed others.

Work exercise: Rebuild a two-week schedule

Give finalists a made-up two-week schedule for [three] install crews and [eight] service technicians with [one] crane pick, [one] equipment delay and a crew lead out sick. Ask them to rebuild it and explain the tradeoffs in [25] minutes.

Production Manager

6 questions · Plan the week across jobs
Job description
  1. Walk me through how you'd plan a rooftop unit replacement on an occupied building, from order to startup.

    Technical · Planning a rooftop replacement

    Strong answer
    Confirms unit and curb adapter fit, electrical and gas, structure and roofing work, crane and permit, the owner's shutdown window, the safety plan, startup and inspection.
    Red flags
    Orders the unit and schedules the crew.
  2. Your job is behind, and the forecast shows high winds on crane day. What do you do?

    Situational · Weather and crane safety

    Strong answer
    Follows the crane operator's and company wind limits, reschedules, informs the owner and general contractor, and doesn't let the schedule decide.
    Red flags
    Goes ahead to stay on schedule.
  3. Three commercial installs are behind and you have one extra crew. How do you decide where it goes?

    Situational · Spreading crews across jobs

    Strong answer
    Weighs contract penalties, customer impact, which delays are truly crew-related, and what the crew is qualified for, then explains the choice to the other jobs.
    Red flags
    Sends it to whoever complains loudest.
  4. An inspector requires a change that isn't on the drawings. What do you do?

    Situational · Inspector-required changes

    Strong answer
    Gets the requirement in writing, tells the project manager so it goes through an RFI or change order, makes the fix, and documents the cost.
    Red flags
    Makes the change and absorbs the cost without telling anyone.
  5. Tell me about the change you made when one of your commercial installs had a quality failure after turnover.

    Behavioral · Learning from failures

    Strong answer
    Explains the failure, the root cause, how they made it right, and the step they added to prevent it.
    Red flags
    Blames the equipment or the customer.
  6. Tell me about a time you had to coach a field supervisor who wasn't enforcing standards like lockout, roof safety or startup sheets.

    Behavioral · Leading supervisors

    Strong answer
    Showed specific examples, set clear expectations, backed them up with the crew, and followed up.
    Red flags
    Enforced the standards themselves and bypassed the supervisor.

Work exercise: Plan the week across jobs

Give finalists a made-up schedule for [four] commercial jobs with crew hours, [one] delayed delivery and [one] failed inspection. Ask them to plan the week and write the morning safety briefing for one crew in [25] minutes.

Project Manager

6 questions · Mark up a submittal
Job description
  1. Walk me through how you review an equipment submittal before you release the order.

    Technical · Submittal review

    Strong answer
    Checks model, capacity, voltage and electrical data, curb and dimensions, weight, options and controls against the drawings and specs, and flags conflicts before submitting.
    Red flags
    Forwards the supplier's submittal without checking it.
  2. You're planning a weekend crane pick to replace four rooftop units on an occupied building. What do you line up?

    Situational · Planning a crane pick

    Strong answer
    Crane and lift plan, permits and any street closure, curb adapters, the roofer, electrical and gas disconnects, the shutdown window and tenant notices, crew and a weather backup date.
    Red flags
    Books the crane and the crew.
  3. The general contractor asks you to add controls points that aren't in your scope and says to just get it done. What do you do?

    Situational · Protecting scope

    Strong answer
    Documents the request, prices it, gets a signed change order or written directive before the work, and tracks it.
    Red flags
    Does the work and hopes to bill it later.
  4. A week before turnover, the commissioning agent fails your economizer sequence tests. What do you do?

    Situational · Commissioning failures

    Strong answer
    Reviews the results with the controls subcontractor and lead technician, schedules fixes and a retest, updates the general contractor on schedule impact, and documents it.
    Red flags
    Argues the test was wrong without checking.
  5. Tell me about a job where closeout dragged on long after your crews were gone.

    Behavioral · Closeout

    Strong answer
    Names what held it up (balance report, O&M manuals, warranty letters, punch list), owns their part, and the change they made, such as starting closeout documents at submittal time.
    Red flags
    Blames others with no change in their own approach.
  6. Tell me about a time your ductwork or piping ran into another trade's work in the field.

    Behavioral · Trade coordination

    Strong answer
    Caught it, worked it out with the other trade and the contractor, sent an RFI when the drawings were wrong, and protected cost and schedule.
    Red flags
    Let the crew reroute without documenting the cost.

Work exercise: Mark up a submittal

Give finalists a made-up equipment schedule and a submittal for [two] rooftop units with [three] planted mismatches, plus a general contractor's email asking for an added unit. Ask them to mark up the submittal and draft the change order email in [30] minutes.

Sales Manager

6 questions · Forecast a quarter
Job description
  1. A rep wants to sign a large multi-site maintenance agreement at a price you think loses money on travel time. What do you do?

    Situational · Pricing multi-site agreements

    Strong answer
    Runs the numbers with the rep, shows where it loses money, and reworks scope, visit timing or price, walking away if it can't be profitable.
    Red flags
    Approves it for the revenue.
  2. You're invited to bid a new-construction job for a general contractor known for shopping low numbers. What do you do?

    Situational · Choosing which bids to chase

    Strong answer
    Decides based on fit, margin and the contractor's history, and if bidding, prices to make money and spells out the scope clearly.
    Red flags
    Bids low to win.
  3. Your team has sold more work this quarter than the install department can deliver. What do you do?

    Situational · Selling within capacity

    Strong answer
    Meets with operations to set realistic dates, tells customers honestly, adjusts what the team pursues, and plans hiring or subcontracting with leadership.
    Red flags
    Keeps selling and leaves it to operations.
  4. Walk me through how you'd forecast a quarter when most of the pipeline is agreement renewals and bid work that takes months to close.

    Technical · Forecasting long sales

    Strong answer
    Uses stage-based probabilities from past results, expected close dates, deal size and renewal timing, and reviews each deal's next step weekly.
    Red flags
    Adds up the reps' gut feelings.
  5. Tell me about a rep you coached who was strong with facility managers but kept losing deals at purchasing.

    Behavioral · Coaching reps

    Strong answer
    Names the specific gaps, such as no contact with purchasing or a weak total-cost case, the coaching (ride-alongs, practice, call planning), and the measurable change.
    Red flags
    Says the rep just needed to work harder.
  6. Tell me about a service agreement account your team lost at renewal.

    Behavioral · Losing key accounts

    Strong answer
    Owns their part, names the warning signs they missed, such as slipping response times or a new facility contact, and explains what they changed in how they manage accounts.
    Red flags
    Blames price or operations entirely.

Work exercise: Forecast a quarter

Give finalists a made-up pipeline of [12] commercial opportunities with stages, values and expected close dates. Ask them to build a quarterly forecast and pick [three] deals they'd coach the rep on, in [25] minutes.

Warehouse Manager

6 questions · Check a delivery
Job description
  1. A rooftop unit arrives on a flatbed with a bent panel, and the driver wants a signature fast. What do you do?

    Situational · Receiving large equipment

    Strong answer
    Inspects before signing, notes the damage on the delivery receipt, photographs it, tells the project manager, and files the freight claim quickly.
    Red flags
    Signs for it clean to let the driver go.
  2. Three crews need material for three different jobs at dawn tomorrow. How do you make sure each leaves with everything?

    Situational · Staging for early starts

    Strong answer
    Pulls and checks each job's material against its order the day before, labels by job, flags shortages to the project manager, and has it loaded or ready for pickup.
    Red flags
    Lets crews pull their own material in the morning.
  3. You see a warehouse worker driving a forklift with an unsecured load stacked high. What do you do?

    Situational · Forklift safety

    Strong answer
    Stops them safely, has the load secured and lowered, coaches on the spot, and checks that the operator is trained and certified.
    Red flags
    Lets it go because nothing fell.
  4. Walk me through how you'd keep inventory accurate when parts go out for both service calls and install jobs.

    Technical · Inventory accuracy

    Strong answer
    Requires every item to be issued to a job or truck, runs regular cycle counts, separates job-staged material from stock, and investigates differences.
    Red flags
    Does a yearly count and adjusts.
  5. Tell me about a time someone on your warehouse team kept sending crews out with the wrong curb adapter, missing fittings or other material errors.

    Behavioral · Leading a warehouse team

    Strong answer
    Looked at the errors to find the cause, retrained on the pick-and-check process, set expectations, followed up, and made a fair decision if it continued.
    Red flags
    Fixed the errors themselves without addressing it.
  6. Tell me about a change you made to how the warehouse stages material for rooftop replacements or new construction jobs.

    Behavioral · Process improvement

    Strong answer
    Names the problem (missed items, late crews), the change (job staging area, labeled pulls, day-before checks), and a measured result like fewer missing-item trips.
    Red flags
    Has never changed how staging works, or can't say whether it helped.

Work exercise: Check a delivery

Give finalists a made-up receiving log, [two] purchase orders and a packing slip with [four] differences. Ask them to check the delivery, say what they'd do about each difference, and plan tomorrow's crew staging, in [20] minutes.

Customer Service Representative

6 questions · Take three commercial calls
Job description
  1. A property manager calls to say a whole floor of offices is hot. What do you ask and record?

    Situational · Capturing a complete work order

    Strong answer
    Building, suite, on-site contact, access and escort rules, the purchase order and not-to-exceed amount, which equipment if known, how many tenants are affected, and after-hours needs.
    Red flags
    Takes a name and address only.
  2. A customer asks whether their maintenance agreement covers a compressor replacement. How do you answer?

    Situational · Explaining agreement coverage

    Strong answer
    Checks the agreement before answering, explains what's covered and what isn't in plain words, and routes pricing questions to the right person.
    Red flags
    Guesses yes or no.
  3. A tenant, not your customer, calls you directly and yells about the temperature in their office. What do you do?

    Situational · Who can authorize work

    Strong answer
    Stays calm, takes the details, explains that the property manager authorizes work, notifies the property manager, and logs the call.
    Red flags
    Sends a technician without authorization, or brushes the tenant off.
  4. Walk me through how you'd set up a new commercial customer so technicians and billing have what they need.

    Technical · Setting up accounts

    Strong answer
    Contacts, billing address and portal, purchase order rules, site access and hours, equipment list, agreement terms, tax-exempt status if any, and special instructions.
    Red flags
    Enters only a name and phone number.
  5. Tell me about a time you kept a customer's open request from falling through the cracks, like a rooftop unit repair quote waiting on approval or a part on order.

    Behavioral · Tracking open work

    Strong answer
    Names the item, how they tracked it (reminders, notes in the system), who they called, and how it got resolved for the customer.
    Red flags
    Assumed someone else was handling it.
  6. Tell me about a time you had to decide whether a commercial customer's problem, like a disputed invoice or repeated complaints, needed a manager.

    Behavioral · Knowing when to escalate

    Strong answer
    Explains how they decided, what they tried first, and how they gave the manager the facts in a short summary.
    Red flags
    Escalates everything, or never escalates.

Work exercise: Take three commercial calls

Have a manager play [three] made-up callers: a property manager with a hot floor, a restaurant whose rooftop unit is leaking into the dining room at lunch, and a tenant calling directly. Give the candidate a work order form and rate their notes and tone over [15] minutes.

Dispatcher

6 questions · Run a commercial board
Job description
  1. Three calls hit at once: a server room cooling alarm, a restaurant's make-up air unit down at lunch, and a routine hot-office complaint. How do you assign them?

    Situational · Prioritizing by risk and contract

    Strong answer
    Ranks by risk and each contract's response time, starting with the server room, checks who's qualified and nearby, gives each customer an honest arrival time, and logs why.
    Red flags
    Takes them in the order they came in.
  2. A technician arrives at an after-hours emergency and can't get into the building. What do you do?

    Situational · After-hours access problems

    Strong answer
    Calls the site contact and the property manager's emergency line, keeps the technician's time logged, updates the customer, and records access instructions for next time.
    Red flags
    Sends the technician home without telling anyone.
  3. A national retail customer requires technicians to check in on its portal, and your technician forgot. What do you do?

    Situational · Customer portal rules

    Strong answer
    Has the technician check in right away, corrects the record if the portal allows, tells the customer if their rules require it, and reminds technicians of each customer's rules.
    Red flags
    Ignores it because the work got done.
  4. Walk me through how you decide which technician gets a chiller call and which gets a rooftop unit call.

    Technical · Matching skills to equipment

    Strong answer
    Checks skills, manufacturer training and certifications, equipment history, likely parts and travel, and won't send a rooftop tech to a chiller just to save time.
    Red flags
    Sends the closest technician.
  5. Tell me how you kept track of everything on your busiest day of emergency calls, like the first heat wave or a cold snap.

    Behavioral · Running a busy board

    Strong answer
    Names specific tools and habits, decisions they made, and how they kept customers and technicians updated.
    Red flags
    Had no system and relied on memory.
  6. Tell me about a time a technician pushed back on a call you assigned, like a chiller or roof job they felt unready or unsafe for.

    Behavioral · Handling pushback

    Strong answer
    Listened to the reason, checked whether it was valid (skills, certifications, safety, hours), found the right technician or escalated, and kept it professional.
    Red flags
    Argued, or gave in without understanding why.

Work exercise: Run a commercial board

Give finalists a made-up board for [five] commercial technicians with each customer's contract response time, then hand them [three] emergency calls one at a time. Ask them to assign and reassign out loud in [15] minutes, explaining each choice.

Bookkeeper

6 questions · Record a short-paid pay application
Job description
  1. Walk me through how you record a monthly progress billing on an install job where the general contractor holds back retainage.

    Technical · Progress billing and retainage

    Strong answer
    Bills the completed work against the schedule of values, records retainage as its own receivable by job, tracks it, and follows up for release at closeout.
    Red flags
    Records only the cash received, or forgets the retainage until someone asks.
  2. A general contractor won't release your payment until you send a lien waiver. The payment hasn't arrived yet. Which waiver do you send, and why?

    Situational · Lien waivers

    Strong answer
    Sends a conditional waiver for that progress payment, on the state's required form where there is one, keeps a waiver log by job, and collects matching waivers from the company's subcontractors.
    Red flags
    Sends an unconditional waiver before the money arrives, or doesn't know the difference.
  3. A property management company keeps rejecting your invoices in its online portal for missing work order numbers. What do you do?

    Situational · Customer portal invoicing

    Strong answer
    Learns that customer's portal rules, works with the office so work order numbers are captured at dispatch, resubmits quickly, and tracks rejections until they stop.
    Red flags
    Resubmits the same invoice, or waits for the customer to call.
  4. A technician's timesheet puts a full day on one job, but dispatch shows the technician at two different buildings. What do you do?

    Situational · Job cost coding

    Strong answer
    Checks the dispatch records, asks the technician and supervisor, corrects the coding before payroll and billing go out, and flags the pattern if it repeats.
    Red flags
    Posts the hours as submitted.
  5. Tell me about a time you caught a billing error on a service agreement or pay application before the customer did.

    Behavioral · Owning billing errors

    Strong answer
    Told their manager, corrected and reissued the invoice, contacted the customer if needed, and fixed the step that caused it.
    Red flags
    Left it alone because the customer hadn't noticed.
  6. Tell me how you collected from a general contractor or property management company that kept paying late.

    Behavioral · Collecting from businesses

    Strong answer
    Found out who approves payments, made sure lien waivers, signed tickets and portal steps were complete, followed up on a steady schedule, and brought in the project manager or their manager when needed.
    Red flags
    Sent statements and waited.

Work exercise: Record a short-paid pay application

Give finalists a made-up pay application, schedule of values and a payment that came in short by the retainage and one disputed change order. Ask them to record the payment and explain the open balance in writing in [25] minutes.

Inventory Specialist

6 questions · Build a filter pick list
Job description
  1. A crew starts a large install Monday, and Friday's delivery is short three items. What do you do before the weekend?

    Situational · Short job deliveries

    Strong answer
    Confirms exactly what's missing, finds the parts or approved substitutes elsewhere, tells the project manager and crew, and arranges delivery or pickup before Monday.
    Red flags
    Tells the crew on Monday morning.
  2. The company changes filters on hundreds of units under maintenance agreements. How do you make sure the right filters are on the right truck each week?

    Situational · Filter program logistics

    Strong answer
    Builds filter lists by site and unit, ties orders to the maintenance schedule, stages by route, and updates the list when sizes change.
    Red flags
    Lets technicians figure it out.
  3. You have shelves of unused parts left over from finished jobs. What do you do?

    Situational · Leftover job material

    Strong answer
    Checks return windows with suppliers, returns what it can for credit, restocks useful parts with correct records, and finds out why extra was ordered.
    Red flags
    Leaves them on the shelf.
  4. Walk me through how you'd decide which commercial HVAC parts to keep in stock and which to special-order.

    Technical · Stock vs. special order

    Strong answer
    Weighs how often it's used, cost, supplier lead time and how critical it is to service agreement customers, and reviews the list on a schedule.
    Red flags
    Stocks everything, or special-orders everything.
  5. Tell me about a time job material kept getting charged to the wrong project or service account.

    Behavioral · Job material accuracy

    Strong answer
    Traced it to the source (pulls not tied to job numbers, returns not credited back, unclear labels), changed the step, and checked that it stayed fixed.
    Red flags
    Moved the charges each month without finding the cause, or blamed project managers.
  6. Tell me about a time a crew showed up to a job short on material you staged, like fittings, duct or a curb adapter.

    Behavioral · Working with frustrated technicians

    Strong answer
    Listened, found what actually went wrong, got the material to them fast, and changed something, such as checking pulls against the job list, so it was less likely to happen again.
    Red flags
    Got defensive, or blamed the technician.

Work exercise: Build a filter pick list

Give finalists a made-up maintenance schedule for [ten] sites with unit counts and filter sizes, plus a current stock list. Ask them to build next week's pick list and purchase order in [20] minutes.

Sales Representative

6 questions · Present a maintenance proposal
Job description
  1. Walk me through how you'd survey a building's HVAC equipment to price a maintenance agreement.

    Technical · Surveying a building

    Strong answer
    Lists each unit's make, model, age, capacity and condition, filter sizes and belts, roof access and lift needs, controls, current problems, and what's out of scope.
    Red flags
    Counts units and guesses the rest.
  2. The facility manager loves your proposal, but purchasing will choose on price. What do you do?

    Situational · Selling to more than one decision-maker

    Strong answer
    Helps the facility manager make the case with response times, scope and total cost, meets purchasing if possible, and holds price where the value is real.
    Red flags
    Cuts the price right away.
  3. A prospect asks whether you service a type of equipment your technicians aren't trained on. How do you answer?

    Situational · Honesty about capability

    Strong answer
    Says so honestly, explains what the company does well, and checks with operations about training or partners before promising anything.
    Red flags
    Says yes to win the deal.
  4. You've just sold a new maintenance agreement. What do you hand to operations so the first visit goes well?

    Situational · Handing off new accounts

    Strong answer
    Equipment list, filter sizes, contacts, access and escort rules, the agreed scope and schedule, billing and portal rules, and any problems the customer mentioned.
    Red flags
    The signed contract and nothing else.
  5. Tell me how you kept your longest commercial sale moving from first meeting to signed agreement.

    Behavioral · Keeping long sales moving

    Strong answer
    Explains the stakeholders, the next steps they set at each meeting, and how they stayed useful without being pushy.
    Red flags
    Just kept checking in.
  6. Tell me about a maintenance agreement you lost to a cheaper bid that covered less.

    Behavioral · Learning from losses

    Strong answer
    Compared the scopes line by line, found out why the customer chose the other bid, judged whether they had made the difference clear, and changed how they present scope or qualify buyers.
    Red flags
    Says the customer only cared about price, or matched the low number without comparing scope.

Work exercise: Present a maintenance proposal

Give finalists a made-up equipment list for a small office building with [six] rooftop units of different ages. Allow [15] minutes to prepare, then have a manager play the facility manager in a [15]-minute proposal meeting.

HVAC Apprentice

6 questions · Filter and coil task
Job description
  1. You're helping a technician on a roof and realize you're working close to an unguarded edge. What do you do?

    Situational · Roof safety

    Strong answer
    Stops, moves back, tells the technician, and follows the company's fall protection rules before going on.
    Red flags
    Keeps working so they don't slow the technician down.
  2. Your technician goes for a part, and a building engineer turns the unit's disconnect back on. What do you do?

    Situational · Lockout awareness

    Strong answer
    Tells the engineer the unit is being worked on, doesn't touch the equipment, and tells the technician right away.
    Red flags
    Says nothing because the engineer works there.
  3. A tenant asks you why their office is always cold. What do you say?

    Situational · Talking with building occupants

    Strong answer
    Is polite, doesn't guess or promise anything, and lets the technician or the customer's contact handle it.
    Red flags
    Guesses at the cause or adjusts the thermostat.
  4. In your own words, walk me through how you think an air conditioner moves heat out of a building.

    Technical · Basic refrigeration idea

    Strong answer
    Describes refrigerant picking up heat inside, the compressor pumping it, and the heat leaving outside at the condenser, roughly right. Gaps are fine.
    Red flags
    Shrugs and won't try to reason it out, or shows no curiosity even when given a hint.
  5. On a commercial job, a small slip like a loose panel or a valve left closed can shut down a building's cooling. Tell me about a mistake you made at work, school or volunteering that you had to own up to.

    Behavioral · Learning from mistakes

    Strong answer
    Owns the mistake, explains how they fixed it and what they do differently now.
    Red flags
    Says they don't make mistakes, blames a teacher or coworker, or hid it until someone else found it.
  6. Commercial apprentices spend a lot of time changing filters and carrying parts to roofs. Tell me about a time at work, school or volunteering when you got stuck with the least exciting part of a job.

    Behavioral · Doing the unglamorous work

    Strong answer
    Did it well, understood why it mattered to the team, and didn't need to be reminded.
    Red flags
    Complained, or did it poorly.

Work exercise: Filter and coil task

In your shop, with a training unit locked out, ask finalists to change filters and rinse a coil after a short demo, following your safety rules, then point out [three] parts on a simple wiring diagram. Allow [20] minutes and coach them as they go.

HVAC Technician

6 questions · Find the three-phase faults
Job description
  1. A rooftop unit is running but blowing warm air on a hot afternoon. Walk me through how you diagnose it.

    Technical · Rooftop unit diagnosis

    Strong answer
    Confirms the call for cooling, checks compressor and condenser fan operation, voltage on all three phases, contactor, pressures with superheat and subcooling, coils and airflow, before replacing anything.
    Red flags
    Adds refrigerant or swaps parts first.
  2. Walk me through how you check a three-phase compressor that keeps tripping.

    Technical · Three-phase compressor problems

    Strong answer
    Measures voltage on each leg and the imbalance, compares amps to the nameplate, checks the contactor and terminals, megohm tests the windings to ground, and looks for causes like high head pressure.
    Red flags
    Resets it and leaves.
  3. The building automation system shows a VAV box fully open, but the space is still hot. Where do you start?

    Situational · Controls troubleshooting

    Strong answer
    Checks the actual damper and actuator, the airflow sensor, reheat, supply air temperature and the controller's setpoints and schedule, rather than trusting the screen.
    Red flags
    Trusts the screen and leaves.
  4. At an office building, the property manager asks you to fix something that isn't on the work order. What do you do?

    Situational · Getting extra work authorized

    Strong answer
    Explains it needs approval, gets a purchase order or written OK from the right contact through the office, documents it, and doesn't do unbilled work.
    Red flags
    Does it for free, or refuses rudely.
  5. Tell me about the last time you added refrigerant to a large commercial system. Walk me through what you did and what you recorded.

    Behavioral · Refrigerant records

    Strong answer
    Searched for the leak before adding, recorded the amount added, leak location and repair, followed the leak repair and record rules that apply to that system and refrigerant, and did a follow-up check on the repair.
    Red flags
    Topped it off without finding the leak or recording it.
  6. Tell me about the hardest problem you've solved on a commercial HVAC system, like a chiller, rooftop unit or controls issue.

    Behavioral · Solving hard problems

    Strong answer
    Names the equipment and symptoms, the logical steps, the tools used, and how they confirmed the fix.
    Red flags
    Is vague, or the problem went away on its own.

Work exercise: Find the three-phase faults

Set up a training unit or bench board in your shop with [two] planted faults, such as a failed contactor coil and a lost phase. Ask finalists to find them with their meter, following your lockout procedure and explaining each step, in [30] minutes. Allow live readings only where your safety rules allow and a supervisor is present; otherwise use de-energized checks.

Lead HVAC Technician

6 questions · Find the root cause
Job description
  1. A chiller trips on low refrigerant pressure several times a week. Walk me through how you'd find the cause.

    Technical · Chiller diagnosis

    Strong answer
    Reviews alarm history and trends, checks chilled water flow and temperatures, approach, charge and leaks, the expansion valve and sensors, and uses the manufacturer's data before changing anything.
    Red flags
    Resets it, or adds refrigerant without finding why.
  2. Walk me through how you start up a new rooftop unit on a construction job.

    Technical · Starting up new equipment

    Strong answer
    Checks electrical and gas connections, motor rotation, belts and pulleys, condensate trap, controls sequence, gas pressure and combustion, refrigeration readings and airflow, and fills out the startup sheet.
    Red flags
    Turns it on and checks for cold air.
  3. A technician you're mentoring is about to condemn a compressor, and you think the real problem is the contactor. What do you do?

    Situational · Teaching in front of customers

    Strong answer
    Asks them to walk through their readings, guides them to test the contactor themselves, and turns it into a lesson without embarrassing them in front of the customer.
    Red flags
    Takes over and fixes it without explaining.
  4. Management is pushing for more billable hours, and you see newer technicians skipping steps on maintenance visits. What do you do?

    Situational · Billable hours vs. quality

    Strong answer
    Raises it with management using examples, shows how skipped steps lead to callbacks, and coaches technicians to do the work right and efficiently.
    Red flags
    Says nothing.
  5. Tell me about a time you set a standard other technicians had to follow, like a startup sheet or a maintenance checklist for rooftop units.

    Behavioral · Raising standards

    Strong answer
    Names the standard (such as a startup checklist), why it was needed, how they got buy-in, and the result.
    Red flags
    Has never done it, or just told people to try harder.
  6. Tell me about a time you explained an expensive repair to a facility manager who needed budget approval.

    Behavioral · Explaining big repairs

    Strong answer
    Explained it plainly, offered options, and gave photos and a written summary the manager could take to their boss.
    Red flags
    Used jargon, or left the manager without anything to show.

Work exercise: Find the root cause

Give finalists a made-up startup sheet and [12] months of service history for a rooftop unit with [three] repeat problems. Ask them to name the likely root causes and explain how they'd teach a newer technician to catch them, in [25] minutes.

Start Hiring Now.

Tell us who you need to hire. Compare plans, then work with HireBus to set up your first role.

Start Hiring Now
Within two weeks, I had interviews and found an amazing candidate.Whitney White, Wise Coatings

Plan details, setup costs, and advertising spend · See pricing